Case study
Đông Hải Steel: eleven years of data they could not prove was unaltered.
Six sites, 340,000 tags, three incompatible historians — two from vendors that no longer exist.
- Steel & metals
- 6 sites
- 17 weeks to cutover
- Live since March 2025
- Client
- Đông Hải Steel
- Sector
- Steel & metals
- Sites
- 6 across 2 provinces
- Engagement
- Survey → deployment → stewardship
- Duration
- 17 weeks to cutover
- Live since
- March 2025
01The problem
Đông Hải had eleven years of process history across three incompatible historians, two of them from vendors that no longer existed. The data was there. What they could not do was prove to their regulator that any given record had not been edited after the fact — so every submission triggered a supplementary evidence request, and each of those consumed roughly forty engineer-days.
02What we did
The survey found 340,000 tags, of which 41% were orphaned — written by equipment nobody was reading. We ingested the three historians in parallel for nine weeks and reconciled them against the shift books, which is where the real disagreements surfaced. Cutover ran line by line over seven weeks with rollback held open through a full production cycle on each.
03What changed
Every write is now signed and replayable to a point in time. Six months after cutover the regulator stopped issuing supplementary requests entirely. The forty engineer-days per submission went to zero, and the team that used to assemble evidence packs now works on kiln optimisation instead.
Case studies
What changed, measured the way the plant measures it.
Every figure below was taken from the client’s own reporting, not ours, and published with their sign-off.
Đông Hải Steel
Steel & metals · 6 sites
Eleven years of unprovable process data turned into accepted regulatory evidence in six months.
−94%
Supplementary evidence requests
Mekong Power
Power generation · 3 plants
Unplanned outage attribution cut from four days of argument to a report generated before the shift ends.
4d → 40m
Time to attribute an outage
Bình Minh Plastics
Chemicals · 9 lines
Batch genealogy assembled automatically, turning a three-week recall simulation into a same-day exercise.
21d → 6h
Recall trace time
Hanoi Water
Water utilities · 18 stations
Regulatory submissions assembled from signed source records rather than re-keyed spreadsheets.
100%
Submissions accepted first pass